Drax carbon capture permit granted for Selby power station
“Robust levels of environmental protection are met,” that is the Environment Agency’s judgement after granting Drax Power Limited a variation to its environmental permit for the bioenergy plant near Selby. Around this part of North Yorkshire, that is more than a technical ruling. It is a key decision for a site that sits squarely inside the region’s arguments over jobs, industry and the move to cleaner power. The permit variation clears Drax to bring carbon capture into the existing plant, subject to the legal conditions set out by the regulator. It does not settle every row around the business, but it does move one of the North’s biggest energy stories another step forward.
At its simplest, the plan is to remove carbon dioxide from the waste gases produced during electricity generation, using a solvent process, so that the majority of that CO2 does not end up in the atmosphere. Drax wants that captured carbon dioxide to be transported away from Selby and stored permanently under the North Sea. For Yorkshire, that makes this more than a company update. It goes to the wider question of how major northern energy and industrial sites are meant to cut emissions without simply shutting their gates. Supporters will see opportunity in that. Critics will say the promises now need to be tested in the real world.
This approval has been a long time coming. Drax first applied to vary its permit in May 2023, and the Environment Agency opened a public consultation at that point. During the review, however, the regulator decided the original application did not contain enough information and asked for a more detailed assessment. That extra scrutiny matters. Drax then submitted a revised air emissions risk assessment, including work on the substances that could be created in the carbon capture plant. A second consultation followed in February 2025, with a third and final consultation on the Agency’s draft decision held earlier in the summer.
The Environment Agency’s position is fairly plain, even if feeling around Drax is anything but. It says permits and permit variations are only issued where the operator can comply with the conditions and has the right systems in place to avoid harm to the environment, human health or wildlife. That legal point is worth spelling out for readers around Selby. The regulator says it may only refuse a permit application if it fails one or more legal requirements under environmental law, including where there would be unacceptable environmental or health impacts. If those requirements are met, the Agency says it is legally obliged to issue the permit.
A decision document has now been published by the Environment Agency, setting out how it reached its conclusion and how it dealt with the concerns raised during consultation. For local residents, campaigners and businesses, that document is where the harder detail now sits: what was challenged, what extra evidence was asked for, and why the regulator believes the final conditions are strong enough. Just as important is the question of enforcement. Environmental permits are not optional guidance. The Agency says its powers include enforcement notices, suspension or revocation of permits, fines and, in the most serious cases, criminal sanctions and prosecution.
For Drax, the ruling keeps a major part of its next chapter in play. The company wants to capture the carbon dioxide released during generation at Selby rather than allow most of it to enter the atmosphere. If the capture system performs as intended, and if the transport and storage network under the North Sea works as planned, Drax will argue it has found a route to stay relevant in a lower-emissions power system. For the North, the stakes run wider than one permit. This is about confidence in industrial decarbonisation, confidence in regulators and confidence that big regional assets are being updated properly rather than simply given a fresh coat of paint.
None of that means the argument is over. A permit variation is a regulatory green light for this part of the project, not the end of public scrutiny. Around Selby, people will still want clear answers on monitoring, transparency and how quickly the authorities would step in if standards slipped. For now, though, the immediate position is clear. The Environment Agency says Drax has shown it can meet the mandatory conditions attached to the permit, and that has been enough to get the variation approved. In a district where energy policy is never some distant Westminster abstraction, that decision carries real local weight.