Drax Selby carbon capture permit granted after consultations

“Robust levels of environmental protection are met,” Environment Agency area manager Ian Foster said as the regulator granted Drax a variation to the environmental permit at its power station near Selby. For North Yorkshire, that means a major regulatory hurdle has now been cleared for carbon capture at one of the region’s most closely watched industrial sites. (gov.uk) The permit documents themselves were published on 5 August 2026, with the Environment Agency’s public announcement following on 14 August 2026. Drax had applied to add carbon capture to its existing permit for the Selby plant, with the captured carbon dioxide intended for permanent storage under the North Sea. (gov.uk)

This decision is important, but it is not a blank cheque. The Environment Agency says it can only issue a permit or permit variation when it is satisfied the operator can meet the conditions and run the plant without harming the environment, human health or wildlife; if the legal tests are met, the agency says it is obliged to issue the permit. (gov.uk) Just as importantly for readers around Selby, the permit does not settle every argument around Drax. The Environment Agency’s own information page says it does not regulate the transport and offshore storage of carbon dioxide, and it does not decide whether biomass fits national energy strategy. Wider rows about burning wood for power sit elsewhere in government, even if they remain very much alive on the ground in Yorkshire. (consult.environment-agency.gov.uk)

The route to this point has been long. The final decision document runs to 163 pages and says the application was formally made on 18 May 2023 after staged submissions dating back to August 2022. A first public consultation then ran from 26 May to 29 June 2023, with an in-person event at Drax Village Hall and an online session the same month. (assets.publishing.service.gov.uk) Regulators were not ready to wave it through first time. The Environment Agency says it asked for more information after deciding Drax had not supplied enough detail, particularly around air emissions. That led to a second consultation from 4 February to 4 March 2025, followed by a third consultation on the agency’s draft decision from 27 May to 24 June 2026. (gov.uk)

That longer timetable matters locally because concerns were raised from more than one direction. In its consultation response, North Yorkshire Council pointed to noise issues and the Environment Agency replied that it had asked for additional information before concluding the carbon capture and carbon dioxide compression plant would not change the current soundscape. The same consultation annex records responses from groups including Just Transition Wakefield and the Stop Burning Trees Coalition. (assets.publishing.service.gov.uk) The criticism from campaigners was not brushed aside as a one-line objection. In the draft decision consultation, the Stop Burning Trees Coalition argued the precautionary principle should apply because the technology is ‘first-of-a-kind’. The Environment Agency’s answer was that the risks could still be assessed and controlled through pre-operational conditions, improvement conditions, emissions monitoring and process monitoring. (assets.publishing.service.gov.uk)

On human health, the decision document leans on wider regulatory scrutiny as well as Drax’s own submissions. It says the revised air impact assessment was consulted on with the UK Health Security Agency in February 2025, and that UKHSA agreed the emissions would not have an adverse impact on human health. (assets.publishing.service.gov.uk) On wildlife and protected sites, Natural England initially agreed there could be an adverse impact on the Thorne Moor SAC from acid deposition, but after further assessment and re-consultation in March 2026 it agreed with the Environment Agency that there would be no adverse impact on the SAC and no likely damage to the Thorne Moor SSSI. That extra round of checking helps explain why this decision took more than three years from formal application to final permit. (assets.publishing.service.gov.uk)

Even with the permit granted, the Environment Agency is plainly not pretending all uncertainty has vanished. Its final decision says there is no real-world operating data for this specific set-up, so Drax will have to confirm the actual concentrations of substances emitted once the carbon capture plant has been running for 12 months and then re-assess impacts if results show a risk of breaching assessment levels. (assets.publishing.service.gov.uk) There is a harder edge to those conditions than the official press release suggests. The decision document says that if commissioning cannot show the plant can comply with the permit conditions, the Environment Agency will not sign off the relevant pre-operational and improvement conditions, and the carbon capture plant will not be able to operate. For a town that has lived alongside Drax for decades, that is the real test of whether oversight has teeth. (assets.publishing.service.gov.uk)

For Drax, this is clearly a significant win. For Selby and nearby villages, it is something more complicated: a promise of cleaner industrial technology set against years of questions about emissions, monitoring and trust. The carbon dioxide is meant to be captured from electricity generation and stored under the North Sea rather than released to the atmosphere, which is why ministers and industry see the scheme as important. (gov.uk) But the permit is better understood as a checkpoint than an end point. The Environment Agency has granted it because, on the evidence in front of it, Drax met the legal tests. Whether that convinces the wider public is another matter entirely, and in this part of Yorkshire people will judge it by what happens next, not by the wording of a Whitehall press release. (gov.uk)